150 MW storage in Henry, IN · In queue since April 2024 · Proposed COD October 2026
150 MW
Capacity
1
Components
Battery
1y 11m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 6m
Pre-Study0%
Queue EntryApr 18, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-01
Project Details
State
IN
County
Henry
Region
MISO
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Point of Interconnection
Greensboro - New Castle 138 138.0kV
Data Source
LBNL + Live