— Project Summary

Queue ID
MISO-J3368
Capacity
199.9 MW
Technology
Wind
Status
active
Location
St. Landry Parish, LA
Region
MISO
Developer
IA Status

BetaActiveWindMISOLBNL + Live

199.9 MW generation in St. Landry Parish, LA · In queue since April 2024 · Proposed COD October 2028

199.9 MW

Capacity

1

Components

Wind

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 6m

Pre-Study0%
Queue EntryApr 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-30

Project Details

State

LA

County

St. Landry Parish

Region

MISO

Developer

Utility

CLECO POWER

Entity

MISO

Point of Interconnection

West Fork

Data Source

LBNL + Live

No news available for this project.