170 MW generation in IN · In queue since May 2014 · Proposed COD December 2010
170 MW
Capacity
1
Components
Coal
11y 10m
In Queue
IA Executed
IA Status
COD target: 2010
Interconnection Timeline
Total Duration
11y 10m
Schedule
185 months past proposed COD
Construction75%
Queue EntryMay 16, 2014
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2010-12-31
Project Details
State
IN
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Wabash River 230 kV Bus
Data Source
LBNL
No news available for this project.