— Project Summary

Queue ID
MISO-J3292
Capacity
193 MW
Technology
Wind
Status
active
Location
Phillips, AR
Region
MISO
Developer
IA Status

BetaActiveWindMISOLBNL + Live

193 MW generation in Phillips, AR · In queue since April 2024 · Proposed COD March 2028

193 MW

Capacity

1

Components

Wind

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 11m

Pre-Study0%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-01

Project Details

State

AR

County

Phillips

Region

MISO

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Point of Interconnection

RITCHIE SWYD - TARLETON 230.0kV

Data Source

LBNL + Live

No news available for this project.