BetaActiveGasMISOLBNL + Live
35 MW generation in Sherburne, MN · In queue since April 2024 · Proposed COD June 2025
35 MW
Capacity
1
Components
Gas
1y 11m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 2m
Schedule
10 months past proposed COD
Pre-Study0%
Queue EntryApr 17, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
MN
County
Sherburne
Region
MISO
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Point of Interconnection
ELK RIVER 14
Data Source
LBNL + Live
No news available for this project.