BetaActiveWindMISOLBNL + Live
249 MW generation in Benton, MN · In queue since April 2024 · Proposed COD September 2028
249 MW
Capacity
1
Components
Wind
1y 11m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 5m
Pre-Study0%
Queue EntryApr 17, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-04
Project Details
State
MN
County
Benton
Region
MISO
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Point of Interconnection
Mud Lake - Benton County (GRE) 230kV
Data Source
LBNL + Live
No news available for this project.