— Project Summary

Queue ID
MISO-J3275
Capacity
249 MW
Technology
Wind
Status
active
Location
Benton, MN
Region
MISO
Developer
IA Status

BetaActiveWindMISOLBNL + Live

249 MW generation in Benton, MN · In queue since April 2024 · Proposed COD September 2028

249 MW

Capacity

1

Components

Wind

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 5m

Pre-Study0%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-04

Project Details

State

MN

County

Benton

Region

MISO

Developer

Utility

GREAT RIVER ENERGY

Entity

MISO

Point of Interconnection

Mud Lake - Benton County (GRE) 230kV

Data Source

LBNL + Live

No news available for this project.