— Project Summary

Queue ID
MISO-J3232
Capacity
500 MW
Technology
Gas
Status
active
Location
Vermillion, IN
Region
MISO
Developer
IA Status

BetaActiveGasMISOLBNL + Live

500 MW generation in Vermillion, IN · In queue since April 2024 · Proposed COD August 2028

500 MW

Capacity

1

Components

Gas

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

Pre-Study0%
Queue EntryApr 11, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-31

Project Details

State

IN

County

Vermillion

Region

MISO

Developer

Utility

DUKE ENERGY INDIANA

Entity

MISO

Point of Interconnection

CAYUGA STATION

Data Source

LBNL + Live

No news available for this project.