— Project Summary

Queue ID
MISO-J3230
Capacity
200 MW
Technology
Wind+Battery
Status
active
Location
Crittenden, AR
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBatteryMISOLBNL + Live

200 MW hybrid in Crittenden, AR · In queue since September 2022 · Proposed COD April 2025

200 MW

Capacity

1

Components

Wind

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 7m

Schedule

12 months past proposed COD

In Study38%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-04-01

Project Details

State

AR

County

Crittenden

Region

MISO

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Point of Interconnection

PARKIN - GILMORE 161.0kV

Data Source

LBNL + Live