— Project Summary

Queue ID
MISO-J3213
Capacity
51 MW
Technology
Gas
Status
active
Location
Hennepin, MN
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveGasMISOLBNL + Live

51 MW generation in Hennepin, MN · In queue since September 2022 · Proposed COD December 2026

51 MW

Capacity

1

Components

Gas

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 3m

Impact Study25%
Queue EntrySep 1, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

MN

County

Hennepin

Region

MISO

Developer

Utility

NORTHERN STATES POWER COMPANY

Entity

MISO

Point of Interconnection

Riverside 115kV Substation

Data Source

LBNL + Live

No news available for this project.