10 MW generation in Dubois, IN · In queue since September 2022 · Proposed COD September 2023
10 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1 year
Schedule
31 months past proposed COD
Impact Study25%
Queue EntrySep 8, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-09-22
Project Details
State
IN
County
Dubois
Region
MISO
Developer
—
Utility
HOOSIER ENERGY
Entity
MISO
Point of Interconnection
HUNTINBURG-ST ANTHONY 69kV (New substation Patoka 69kV)
Data Source
LBNL + Live