BetaActiveWindMISOLBNL + Live
208 MW generation in Clark, WI · In queue since September 2022 · Proposed COD September 2025
208 MW
Capacity
1
Components
Wind
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3 years
Schedule
6 months past proposed COD
Impact Study25%
Queue EntrySep 14, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-15
Project Details
State
WI
County
Clark
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Gardner Park - Stone Lake 345kV Line
Data Source
LBNL + Live
No news available for this project.