— Project Summary

Queue ID
MISO-J3204
Capacity
208 MW
Technology
Wind
Status
active
Location
Clark, WI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveWindMISOLBNL + Live

208 MW generation in Clark, WI · In queue since September 2022 · Proposed COD September 2025

208 MW

Capacity

1

Components

Wind

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3 years

Schedule

6 months past proposed COD

Impact Study25%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-15

Project Details

State

WI

County

Clark

Region

MISO

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Point of Interconnection

Gardner Park - Stone Lake 345kV Line

Data Source

LBNL + Live

No news available for this project.