— Project Summary

Queue ID
MISO-J3185
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Effingham, IL
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryMISOLBNL + Live

150 MW hybrid in Effingham, IL · In queue since September 2022 · Proposed COD February 2027

150 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 5m

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-02-01

Project Details

State

IL

County

Effingham

Region

MISO

Developer

Utility

AMEREN ILLINOIS

Entity

MISO

Point of Interconnection

Effingham - Newton 138KV (4EFFINGHM 347025 -4NEWTON 347831)

Data Source

LBNL + Live

No news available for this project.