— Project Summary

Queue ID
MISO-J3165
Capacity
200 MW
Technology
Solar
Status
active
Location
Breckinridge, KY
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

200 MW generation in Breckinridge, KY · In queue since September 2022 · Proposed COD August 2025

200 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 11m

Schedule

7 months past proposed COD

Impact Study25%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-08-31

Project Details

State

KY

County

Breckinridge

Region

MISO

Developer

Utility

BIG RIVERS ELECTRIC CORPORATION

Entity

MISO

Point of Interconnection

New Hardinsburg 161 kV Substation

Data Source

LBNL + Live

No news available for this project.