— Project Summary

Queue ID
MISO-J3159
Capacity
100 MW
Technology
Battery
Status
active
Location
Dubuque, IA
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveBatteryMISOLBNL + Live

100 MW storage in Dubuque, IA · In queue since September 2022 · Proposed COD June 2027

100 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 9m

Impact Study25%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-30

Project Details

State

IA

County

Dubuque

Region

MISO

Developer

Utility

ITC MIDWEST

Entity

MISO

Point of Interconnection

Gardner 69 kV substation

Data Source

LBNL + Live

No news available for this project.