— Project Summary

Queue ID
MISO-J3137
Capacity
156.3 MW
Technology
Solar
Status
active
Location
Pocahontas, IA
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

156.3 MW generation in Pocahontas, IA · In queue since September 2022 · Proposed COD May 2026

156.3 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-01

Project Details

State

IA

County

Pocahontas

Region

MISO

Developer

Utility

MIDAMERICAN ENERGY CO.

Entity

MISO

Point of Interconnection

Sac - Pocahontas 161 kV

Data Source

LBNL + Live

No news available for this project.