— Project Summary

Queue ID
MISO-J3133
Capacity
120 MW
Technology
Battery
Status
active
Location
Saginaw, MI
Region
MISO
Developer
IA Status

BetaActiveBatteryMISOLBNL + Live

120 MW storage in Saginaw, MI · In queue since September 2022 · Proposed COD August 2026

120 MW

Capacity

1

Components

Battery

3y 6m

In Queue

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 11m

Pre-Study0%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-08-31

Project Details

State

MI

County

Saginaw

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

Murphy to Nelson Road 345 kV

Data Source

LBNL + Live

No news available for this project.