— Project Summary

Queue ID
MISO-J3118
Capacity
160 MW
Technology
Solar+Battery
Status
active
Location
Morehouse Parish, LA
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryMISOLBNL + Live

160 MW hybrid in Morehouse Parish, LA · In queue since September 2022 · Proposed COD June 2026

160 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 9m

In Study38%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-30

Project Details

State

LA

County

Morehouse Parish

Region

MISO

Developer

Utility

ENTERGY LOUISIANA

Entity

MISO

Point of Interconnection

Taping the 'Galion / 3GALION (337444)' to 'Oak Grove / 3OAK_GROVE! (337445)' 115kV line

Data Source

LBNL + Live

No news available for this project.