BetaActiveSolarBatteryMISOLBNL + Live
300 MW hybrid in Greene, IN · In queue since September 2022 · Proposed COD June 2026
300 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 9m
Impact Study25%
Queue EntrySep 15, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
IN
County
Greene
Region
MISO
Developer
—
Utility
HOOSIER ENERGY
Entity
MISO
Point of Interconnection
Taping 'Sandborn Primary / 07SAND61 (248465)' to 'Worthington Primary / 07WORTH (248784)' 161kV line
Data Source
LBNL + Live
No news available for this project.