BetaActiveWindMISOLBNL + Live
252 MW generation in Peoria, IL · In queue since September 2022 · Proposed COD October 2026
252 MW
Capacity
1
Components
Wind
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 1m
Impact Study25%
Queue EntrySep 12, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-31
Project Details
State
IL
County
Peoria
Region
MISO
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Point of Interconnection
Fargo to Sandburg 345kV
Data Source
LBNL + Live
No news available for this project.