— Project Summary

Queue ID
MISO-J3070
Capacity
150 MW
Technology
Wind
Status
active
Location
Morton, ND
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveWindMISOLBNL + Live

150 MW generation in Morton, ND · In queue since September 2022 · Proposed COD February 2025

150 MW

Capacity

1

Components

Wind

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 5m

Schedule

13 months past proposed COD

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-02-27

Project Details

State

ND

County

Morton

Region

MISO

Developer

Utility

MINNESOTA POWER INC.

Entity

MISO

Point of Interconnection

Square Butte East 230 kV

Data Source

LBNL + Live

No news available for this project.