150 MW generation in Morton, ND · In queue since September 2022 · Proposed COD February 2025
150 MW
Capacity
1
Components
Wind
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 5m
Schedule
13 months past proposed COD
Impact Study25%
Queue EntrySep 15, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-02-27
Project Details
State
ND
County
Morton
Region
MISO
Developer
—
Utility
MINNESOTA POWER INC.
Entity
MISO
Point of Interconnection
Square Butte East 230 kV
Data Source
LBNL + Live