BetaActiveSolarMISOLBNL + Live
150 MW generation in Chisago, MN · In queue since January 2024 · Proposed COD June 2026
150 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 5m
Impact Study25%
Queue EntryJan 9, 2024
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
MN
County
Chisago
Region
MISO
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Point of Interconnection
Rush City 230 kV
Data Source
LBNL + Live
No news available for this project.