BetaActiveSolarBatteryMISOLBNL + Live
100 MW hybrid in Perry, MS · In queue since September 2022 · Proposed COD June 2027
100 MW
Capacity
1
Components
Solar
3y 6m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 9m
Pre-Study0%
Queue EntrySep 14, 2022
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
MS
County
Perry
Region
MISO
Developer
—
Utility
COOPERATIVE ENERGY
Entity
MISO
Point of Interconnection
Hintonville to Waynesboro 161 kV
Data Source
LBNL + Live
No news available for this project.