— Project Summary

Queue ID
MISO-J3028
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Perry, MS
Region
MISO
Developer
IA Status

BetaActiveSolarBatteryMISOLBNL + Live

100 MW hybrid in Perry, MS · In queue since September 2022 · Proposed COD June 2027

100 MW

Capacity

1

Components

Solar

3y 6m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 9m

Pre-Study0%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

MS

County

Perry

Region

MISO

Developer

Utility

COOPERATIVE ENERGY

Entity

MISO

Point of Interconnection

Hintonville to Waynesboro 161 kV

Data Source

LBNL + Live