— Project Summary

Queue ID
MISO-J3007
Capacity
100 MW
Technology
Battery
Status
active
Location
Mason, MI
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryMISOLBNL + Live

100 MW storage in Mason, MI · In queue since August 2022 · Proposed COD May 2025

100 MW

Capacity

1

Components

Battery

3y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 9m

Schedule

11 months past proposed COD

In Study38%
Queue EntryAug 25, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-05-15

Project Details

State

MI

County

Mason

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

PERE MARQUETTE - LINDEMAN 138.0kV

Data Source

LBNL + Live

No news available for this project.