BetaActiveBatteryMISOLBNL + Live
100 MW storage in Mason, MI · In queue since August 2022 · Proposed COD May 2025
100 MW
Capacity
1
Components
Battery
3y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 9m
Schedule
11 months past proposed COD
In Study38%
Queue EntryAug 25, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-05-15
Project Details
State
MI
County
Mason
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
PERE MARQUETTE - LINDEMAN 138.0kV
Data Source
LBNL + Live