— Project Summary

Queue ID
MISO-J2998
Capacity
200 MW
Technology
Battery
Status
active
Location
St. Clair, IL
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveBatteryMISOLBNL + Live

200 MW storage in St. Clair, IL · In queue since September 2022 · Proposed COD September 2025

200 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3 years

Schedule

6 months past proposed COD

Impact Study25%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-15

Project Details

State

IL

County

St. Clair

Region

MISO

Developer

Utility

AMEREN ILLINOIS

Entity

MISO

Point of Interconnection

Fayetteville Bee Hollow Road 138kV Substation

Data Source

LBNL + Live

No news available for this project.