BetaActiveWindMISOLBNL + Live
175 MW generation in Humboldt, IA · In queue since September 2022 · Proposed COD March 2025
175 MW
Capacity
1
Components
Wind
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 6m
Schedule
13 months past proposed COD
Impact Study25%
Queue EntrySep 14, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-03-15
Project Details
State
IA
County
Humboldt
Region
MISO
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Point of Interconnection
J2256 POI - Irvington 345kV line
Data Source
LBNL + Live
No news available for this project.