BetaActiveSolarMISOLBNL + Live
250 MW generation in Posey, IN · In queue since September 2022 · Proposed COD August 2026
250 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 11m
Impact Study25%
Queue EntrySep 15, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-08-15
Project Details
State
IN
County
Posey
Region
MISO
Developer
—
Utility
Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
Entity
MISO
Point of Interconnection
AB Brown 345 - Gibson(Duke Terminal) 345 kV
Data Source
LBNL + Live
No news available for this project.