— Project Summary

Queue ID
MISO-J2966
Capacity
450 MW
Technology
Solar
Status
active
Location
Quitman, MS
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

450 MW generation in Quitman, MS · In queue since September 2022 · Proposed COD October 2025

450 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 1m

Schedule

5 months past proposed COD

In Study38%
Queue EntrySep 8, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-15

Project Details

State

MS

County

Quitman

Region

MISO

Developer

Utility

ENTERGY MISSISSIPPI, LLC.

Entity

MISO

Point of Interconnection

Batesville to Moon Lake ss 230kV Line

Data Source

LBNL + Live

No news available for this project.