150 MW generation in Saline, AR · In queue since November 2023 · Proposed COD September 2026
150 MW
Capacity
1
Components
Solar
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 10m
In Study38%
Queue EntryNov 7, 2023
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
AR
County
Saline
Region
MISO
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Point of Interconnection
WRIGHTSVILLE √¢?? WHITE BLUFF EHV 115 KV
Data Source
LBNL + Live