BetaActiveGasMISOLBNL + Live
205 MW generation in Rock, WI · In queue since September 2022 · Proposed COD April 2026
205 MW
Capacity
1
Components
Gas
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 7m
In Study38%
Queue EntrySep 15, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-04-01
Project Details
State
WI
County
Rock
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Rock River 138 kV Substations 1 (6 RICE) and 2 (5 RICE)
Data Source
LBNL + Live