BetaActiveWindMISOLBNL + Live
200 MW generation in Henderson, KY · In queue since September 2022 · Proposed COD October 2025
200 MW
Capacity
1
Components
Wind
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 1m
Schedule
6 months past proposed COD
Impact Study25%
Queue EntrySep 14, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-01
Project Details
State
KY
County
Henderson
Region
MISO
Developer
—
Utility
Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
Entity
MISO
Point of Interconnection
AB Brown 345 kV - Reid 345 kV
Data Source
LBNL + Live
No news available for this project.