— Project Summary

Queue ID
MISO-J2899
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Calcasieu Parish, LA
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryMISOLBNL + Live

250 MW hybrid in Calcasieu Parish, LA · In queue since September 2022 · Proposed COD April 2026

250 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 7m

In Study38%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-04-30

Project Details

State

LA

County

Calcasieu Parish

Region

MISO

Developer

Utility

ENTERGY LOUISIANA

Entity

MISO

Point of Interconnection

Chalkley Co to Goos Ferry 230kV

Data Source

LBNL + Live

No news available for this project.