BetaActiveSolarMISOLBNL + Live
50 MW generation in Kenosha, WI · In queue since January 2024 · Proposed COD June 2026
50 MW
Capacity
1
Components
Solar
2y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 5m
In Study38%
Queue EntryJan 9, 2024
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
WI
County
Kenosha
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
138kV line X-137 (Spring Valley to State Line)
Data Source
LBNL + Live
No news available for this project.