— Project Summary

Queue ID
MISO-J2885
Capacity
130 MW
Technology
Solar
Status
active
Location
Red Lake, MN
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

130 MW generation in Red Lake, MN · In queue since September 2022 · Proposed COD January 2025

130 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 4m

Schedule

15 months past proposed COD

Impact Study25%
Queue EntrySep 6, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-01-10

Project Details

State

MN

County

Red Lake

Region

MISO

Developer

Utility

OTTER TAIL POWER COMPANY

Entity

MISO

Point of Interconnection

Plummer Pipe

Data Source

LBNL + Live