BetaActiveSolarMISOLBNL + Live
130 MW generation in Red Lake, MN · In queue since September 2022 · Proposed COD January 2025
130 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 4m
Schedule
15 months past proposed COD
Impact Study25%
Queue EntrySep 6, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-10
Project Details
State
MN
County
Red Lake
Region
MISO
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Point of Interconnection
Plummer Pipe
Data Source
LBNL + Live
No news available for this project.