— Project Summary

Queue ID
MISO-J2865
Capacity
375 MW
Technology
Solar
Status
active
Location
Ouachita, AR
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

375 MW generation in Ouachita, AR · In queue since September 2022 · Proposed COD August 2027

375 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 11m

In Study38%
Queue EntrySep 13, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-08-31

Project Details

State

AR

County

Ouachita

Region

MISO

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Point of Interconnection

El Dorado EHV - McNeil EHV 500kV

Data Source

LBNL + Live

No news available for this project.