— Project Summary

Queue ID
MISO-J2845
Capacity
200 MW
Technology
Solar
Status
active
Location
Freeborn, MN
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

200 MW generation in Freeborn, MN · In queue since September 2022 · Proposed COD October 2025

200 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 1m

Schedule

5 months past proposed COD

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-15

Project Details

State

MN

County

Freeborn

Region

MISO

Developer

Utility

ITC MIDWEST

Entity

MISO

Point of Interconnection

Hayward - Adams 161kV line

Data Source

LBNL + Live