BetaActiveSolarMISOLBNL + Live
140 MW generation in Calhoun, MI · In queue since August 2022 · Proposed COD February 2025
140 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 6m
Schedule
13 months past proposed COD
Impact Study25%
Queue EntryAug 30, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-02-15
Project Details
State
MI
County
Calhoun
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
Argenta - Verona 138kV Line
Data Source
LBNL + Live