— Project Summary

Queue ID
MISO-J2815
Capacity
140 MW
Technology
Solar
Status
active
Location
Calhoun, MI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

140 MW generation in Calhoun, MI · In queue since August 2022 · Proposed COD February 2025

140 MW

Capacity

1

Components

Solar

3y 7m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 6m

Schedule

13 months past proposed COD

Impact Study25%
Queue EntryAug 30, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-02-15

Project Details

State

MI

County

Calhoun

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

Argenta - Verona 138kV Line

Data Source

LBNL + Live