BetaActiveSolarMISOLBNL + Live
220 MW generation in Kalamazoo, MI · In queue since September 2022 · Proposed COD February 2026
220 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 5m
Schedule
1 months past proposed COD
Impact Study25%
Queue EntrySep 7, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-15
Project Details
State
MI
County
Kalamazoo
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
Argenta Morrow 138 kV
Data Source
LBNL + Live
No news available for this project.