BetaActiveSolarBatteryMISOLBNL + Live
100 MW hybrid in Sunflower, MS · In queue since September 2022 · Proposed COD December 2025
100 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 3m
Schedule
4 months past proposed COD
In Study38%
Queue EntrySep 14, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-06
Project Details
State
MS
County
Sunflower
Region
MISO
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Point of Interconnection
CLEVELAND/SOUTH - STEINER (CE) 115.0kV
Data Source
LBNL + Live
No news available for this project.