BetaActiveSolarMISOLBNL + Live
170 MW generation in Arkansas, AR · In queue since September 2023 · Proposed COD September 2026
170 MW
Capacity
1
Components
Solar
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3 years
In Study38%
Queue EntrySep 12, 2023
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
AR
County
Arkansas
Region
MISO
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Point of Interconnection
Woodward-Ricuskey 230 kV Line
Data Source
LBNL + Live
No news available for this project.