— Project Summary

Queue ID
MISO-J2754
Capacity
170 MW
Technology
Solar
Status
active
Location
Polk, TX
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

170 MW generation in Polk, TX · In queue since September 2022 · Proposed COD January 2026

170 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 4m

Schedule

3 months past proposed COD

In Study38%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-01

Project Details

State

TX

County

Polk

Region

MISO

Developer

Utility

ENTERGY TEXAS, INC.

Entity

MISO

Point of Interconnection

138kV Bragg - SHECO Menard Line

Data Source

LBNL + Live

No news available for this project.