— Project Summary

Queue ID
MISO-J2752
Capacity
130 MW
Technology
Solar
Status
active
Location
Montgomery, MS
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

130 MW generation in Montgomery, MS · In queue since September 2022 · Proposed COD January 2026

130 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 4m

Schedule

3 months past proposed COD

In Study38%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-01

Project Details

State

MS

County

Montgomery

Region

MISO

Developer

Utility

ENTERGY MISSISSIPPI, LLC.

Entity

MISO

Point of Interconnection

ELLIOTT SS-SAWYER SS(CE) 115 kv line (New Substation Added)

Data Source

LBNL + Live

No news available for this project.