BetaActiveBatteryMISOLBNL + Live
150 MW storage in Jackson, MN · In queue since September 2022 · Proposed COD July 2025
150 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 10m
Schedule
8 months past proposed COD
Impact Study25%
Queue EntrySep 15, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-07-24
Project Details
State
MN
County
Jackson
Region
MISO
Developer
—
Utility
Southern Illinois Power Cooperative
Entity
MISO
Point of Interconnection
Jackson North 161kV Substation
Data Source
LBNL + Live
No news available for this project.