BetaActiveBatteryMISOLBNL + Live
200 MW storage in St. Clair, MI · In queue since September 2022 · Proposed COD January 2025
200 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 4m
Schedule
15 months past proposed COD
Impact Study25%
Queue EntrySep 8, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-01
Project Details
State
MI
County
St. Clair
Region
MISO
Developer
—
Utility
ITC
Entity
MISO
Point of Interconnection
BUNCE (120kV) (Bus Name: 19BUNCE1)
Data Source
LBNL + Live