— Project Summary

Queue ID
MISO-J2679
Capacity
100 MW
Technology
Solar
Status
active
Location
Livingston, MI
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

100 MW generation in Livingston, MI · In queue since September 2022 · Proposed COD April 2027

100 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 7m

In Study38%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-15

Project Details

State

MI

County

Livingston

Region

MISO

Developer

Utility

ITC

Entity

MISO

Point of Interconnection

COLFAX to Madrid 120 kV

Data Source

LBNL + Live

No news available for this project.