BetaActiveSolarMISOLBNL + Live
150 MW generation in Delta, MI · In queue since September 2022 · Proposed COD November 2025
150 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 2m
Schedule
5 months past proposed COD
In Study38%
Queue EntrySep 14, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-01
Project Details
State
MI
County
Delta
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Chandler 138 kV
Data Source
LBNL + Live
No news available for this project.