— Project Summary

Queue ID
MISO-J2670
Capacity
223 MW
Technology
Solar
Status
active
Location
Mason, MI
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

223 MW generation in Mason, MI · In queue since September 2022 · Proposed COD November 2025

223 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 2m

Schedule

5 months past proposed COD

In Study38%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-01

Project Details

State

MI

County

Mason

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

Ludington to Keystone 345 kV

Data Source

LBNL + Live

No news available for this project.