BetaActiveSolarMISOLBNL + Live
105.8 MW generation in Bradley, AR · In queue since September 2022 · Proposed COD June 2025
105.8 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 9m
Schedule
10 months past proposed COD
In Study38%
Queue EntrySep 9, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
AR
County
Bradley
Region
MISO
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Point of Interconnection
AECC HERMITAGE SOUTH - HILO 115.0kV
Data Source
LBNL + Live
No news available for this project.