— Project Summary

Queue ID
MISO-J2628
Capacity
250 MW
Technology
Battery
Status
active
Location
Huron, MI
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryMISOLBNL + Live

250 MW storage in Huron, MI · In queue since September 2022 · Proposed COD July 2024

250 MW

Capacity

1

Components

Battery

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 10m

Schedule

21 months past proposed COD

In Study38%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-07-01

Project Details

State

MI

County

Huron

Region

MISO

Developer

Utility

ITC

Entity

MISO

Point of Interconnection

Rapson 345 kV

Data Source

LBNL + Live

No news available for this project.