— Project Summary

Queue ID
MISO-J2599
Capacity
216 MW
Technology
Solar
Status
active
Location
Redwood, MN
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

216 MW generation in Redwood, MN · In queue since September 2022 · Proposed COD June 2026

216 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 9m

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-30

Project Details

State

MN

County

Redwood

Region

MISO

Developer

Utility

NORTHERN STATES POWER COMPANY

Entity

MISO

Point of Interconnection

Lyon County 345kV Substation

Data Source

LBNL + Live

No news available for this project.