— Project Summary

Queue ID
MISO-J2587
Capacity
200 MW
Technology
Battery
Status
active
Location
Vigo, IN
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveBatteryMISOLBNL + Live

200 MW storage in Vigo, IN · In queue since September 2022 · Proposed COD April 2025

200 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 7m

Schedule

12 months past proposed COD

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-04-01

Project Details

State

IN

County

Vigo

Region

MISO

Developer

Utility

DUKE ENERGY INDIANA

Entity

MISO

Point of Interconnection

Sugar Creek - Cayuga 345 kV Transmission Line

Data Source

LBNL + Live

No news available for this project.